Negotiations between Daewoo Engineering & Construction and Korea Hydro & Nuclear Power regarding the construction contract for the Dukovany Nuclear Power Plant in the Czech Republic have collapsed, hindering Daewoo's strategy for expanding its overseas business. Daewoo has requested a renegotiation with Korea Hydro and expressed its willingness to participate in future competitive bidding, but disagreements over construction costs and expenses related to design changes have left the company's return to the project uncertain.
According to the construction industry on the 29th, Korea Hydro has ended negotiations with the Daewoo-Doosan Energy consortium for the new nuclear power plant construction contract in the Czech Republic. A Daewoo representative stated, "We have requested Korea Hydro to resume negotiations smoothly."
The core issue in the failed negotiations was the gap in construction costs and the burden of expenses due to design changes. Daewoo explained that the revised proposal submitted by the deadline differed significantly from the amount suggested by Korea Hydro. They emphasized that the APR1000 model, being the first commercial nuclear power plant of its kind, requires careful examination of construction quantities and costs. Daewoo argued that accepting conditions that impose a high burden of increased quantities due to design changes without adjusting construction costs is difficult.
There are conflicting views regarding the negotiation timeline. Daewoo claimed that after receiving a revised proposal from Korea Hydro on the 7th, it requested an extension of the review and negotiation period until the end of the year, but this was not accepted. In contrast, Korea Hydro stated that despite sufficient discussions, they could not reach an agreement and decided to end negotiations to prevent project delays, asserting that they did not unfairly transfer risks to the contractor.
The collapse of these negotiations is expected to weigh on Daewoo's plans for expanding its overseas orders. Since 2018, Daewoo has been preparing to participate in the Czech nuclear project, aiming to secure experience in European nuclear construction and pursue subsequent projects. Without securing construction experience in the Czech Republic, there are concerns that their plans to expand into the European nuclear market may be disrupted.
From a performance perspective, securing large overseas contracts is crucial at this time. Daewoo's cumulative operating profit for the third quarter of this year increased by 131.3% compared to the same period last year, but revenue decreased by 7.9%. The annual order target has been raised to 27 trillion won, but the achievement rate as of the third quarter stands at 46.2%. Although the construction contract in the Czech Republic has not yet been finalized, the lack of expected new orders and long-term revenue growth has introduced variables.
Daewoo has stated that it is not yet prepared to officially explain its response plan following the failed renegotiation. However, it has kept the possibility of participating in new competitive bidding open. A Daewoo representative remarked, "If there is an opportunity to participate, we will prepare, and there is no reason for Daewoo not to do so."