Interview with Kim Hyun-ki, Gangnam District Chief: "Reconstruction, Time is Money"


"We will reduce the time of administration and the time of conflict as well."

Kim Hyun-ki, the chief of Gangnam District, announced plans to simultaneously shorten the permit processing time for reconstruction and resolve resident conflicts, aiming to start construction at 15 reconstruction sites totaling 27,330 housing units by 2030. His plan includes reducing waiting times through sequential reviews by departments and preventing long-term project delays through expert consultations and on-site communication.

 
In an interview with this publication on the 16th, Kim introduced the 'Gangnam Reconstruction Acceleration Project,' which encompasses these goals.
 
He stated, "Reconstruction is not just about building new apartments; it is a matter of property rights and residency for residents, as well as the future of Gangnam." He added, "While I cannot change the laws, systems, market conditions, or residents' decision-making, I can reduce the time for administrative processing and support."
 
A representative case presented by Gangnam District is the approval of the Eunma Apartment project plan. According to the district, the processing time for the Eunma Apartment approval was 27 days, which is 55% shorter than the standard processing time of 60 days. This was achieved by conducting public reviews and consultations with related agencies simultaneously after preliminary preparations.
 
The approval for the promotion committees of Ilwon Hansol, Daechi Seonggyeong, and Ilwon Sangnoksu was also processed in about 10 days, approximately 67% shorter than the standard processing time of 30 days. The approval for the establishment of the Ilwon Garam association also took 10 days.
 
This achievement in reducing the administrative processing time for individual permits is distinct from the overall reconstruction project duration, which includes everything from planning to completion.
 
Gangnam District aims to reduce the administrative processing time for major permits by over 30% compared to the standard. The approval for promotion committees and association establishment is planned to be shortened from 30 days to 21 days, while project plan approvals and management plan approvals will be reduced from 60 days to 42 days.
 
Kim also mentioned past instances where some reconstruction projects in Gangnam took 6 to 8 months for project plan approvals. However, he emphasized that conditions vary by project, stating, "If administration changes, the waiting time will also shorten."
 
At the center of this change is the 'Acceleration Task Force' directly under the district chief. Kim stated that he initiated the project on his first day in office, July 1, with his first official decision, and took on the role of head to establish a collaborative system among related departments, including reconstruction, roads, traffic, environment, parks, and flood control.
 
The key is to shift from a sequential review and repeated revisions and negotiations by each department to a collaborative examination and resolution of issues specific to each project. The task force examines administrative procedures and on-site issues through rapid response teams, communication teams, and expert support groups. An organizational restructuring is also planned for January to prioritize reconstruction as the top agenda item for the district administration.
 
Kim explained that he receives daily reports on the progress of each project at 9 a.m. and checks the project schedule and major issues on the reconstruction status board set up in the district chief's office. If there are signs of delays in negotiations or project stagnation, he discusses immediate response directions with the relevant departments.
 
He stated, "We move before problems arise, not after they occur."
 
The impetus for Gangnam District's speed improvement efforts stems from the reality that many projects are stuck in the early to mid-stages.
 
Kim noted that there are currently 53 reconstruction projects in the district, and the total number of maintenance projects, including small-scale housing maintenance and remodeling, is 103. He mentioned that among the 53 reconstruction projects, 39 are in the early to mid-stages, involving planning, promotion committee formation, and association establishment preparations.
 
He cited the Dogok Samho Apartment, which received completion approval on October 26, as an example, highlighting the burden on residents due to long-term projects. This complex took 14 years from the start of safety inspections in 2012 to receive completion approval.
 
He remarked, "Time is cost in reconstruction," adding, "As time extends, the burden on residents and the weight of waiting increase."
 
Another aspect of the project is conflict resolution. Even if administrative processing speeds up, if conflicts among residents regarding interests or rights cause projects to stall for years, it becomes difficult to shorten the overall project duration.
 
To address this, Gangnam District has formed a rapid response expert support group consisting of 41 specialists in conflict management, law, architecture, urban planning, appraisal, and transportation. They support problem-solving for associations and residents through conflict mediation, expert consultations, and free consultations for residents.
 
The district supported an agreement between the Daechi Sangyong 1st association and commercial establishments in July and provided expert advice on the issue of member status succession for the integrated reconstruction of Daechi Woosung 1st and Sangyong 2nd in September.
 
Training for conflict prevention is also being conducted. The district runs a maintenance project academy for residents four times a year and offers a two-session expert training course for association executives and promotion committee members. The aim is to reduce misunderstandings arising from a lack of information and enhance the practical capabilities of project stakeholders by improving understanding of systems and procedures.
 
Information is also being provided through text services, satisfaction surveys on reconstruction policies, and on-site meetings. Kim stated that he is listening to residents' opinions in areas such as Eunma Apartment, Apgujeong reconstruction zone, the northern section of Yangjaecheon, and Suseo development area, and that he held a meeting last month under the theme 'Gangnam Reconstruction: Finding Solutions Together.'
 
Gangnam District has set a goal of starting construction at a total of 15 sites and 27,330 housing units by 2030. The annual breakdown includes three sites with 2,560 units in 2027, two sites with 8,550 units in 2028, six sites with 5,600 units in 2029, and four sites with 10,620 units in 2030.
 
The district plans to check the progress schedule for each project and support the necessary permits to ensure they lead to actual construction.

Kim emphasized, "We are not just rushing to stamp the permit documents; we are working to ensure that reconstruction projects lead to actual construction." He added, "In response to residents' urgent question of when their apartment reconstruction will happen, we will answer with speed and execution."