AJP Asia Intelligence Agency

S-Oil Advances 9 Trillion Won Shahin Project Amid Ongoing Conflict

Amid the prolonged conflict in the Middle East and the unstable situation in Saudi Arabia, S-Oil, which has Saudi state-owned oil company Aramco as its major shareholder, is set to launch a 9 trillion won (KRW) petrochemical project in South Korea. This move contrasts with the domestic petrochemical industry, which is pushing for facility reductions and business restructuring due to a long-term downturn.


According to industry sources on the 18th, S-Oil will hold a completion ceremony for the Shahin Project on the 25th in Seoul, which has been constructed in the Onsan National Industrial Complex in Ulsan. The Shahin Project represents the largest investment in the history of South Korea's petrochemical sector, with a total investment of 9.26 trillion won (KRW).


Initially, there were discussions about not holding the completion ceremony due to the unstable situation in Saudi Arabia. However, it was reported that the decision was made to proceed with the event considering the symbolic significance of the Shahin Project. Key officials from the governments of South Korea and Saudi Arabia, as well as business representatives, are expected to attend the ceremony. The possibility of Saudi Crown Prince Mohammed bin Salman visiting South Korea has also been mentioned, but specific schedules or attendance have not yet been confirmed.


The core of the Shahin Project is the establishment of an 'integrated production system' that links existing refining facilities with new petrochemical plants. This initiative aims not only to increase the production of petrochemical products but also to create a complex production base that connects crude oil refining with the production of petrochemical raw materials and final products.


Notably, the TC2C (Thermal Crude to Chemicals) technology developed by Aramco will be commercially applied for the first time in the world. This technology converts low-value fractions generated during crude oil and refining processes into petrochemical raw materials. It is characterized by its ability to reduce raw material procurement costs and enhance production efficiency by integrating with existing refining facilities.


Once the Shahin Project is fully operational, it will have an annual ethylene production capacity of 1.8 million tons. The overall petrochemical production capacity is expected to increase by approximately 3.2 million tons, raising the share of petrochemical products in S-Oil's total production from about 12% to around 25%.


However, this move contrasts with the restructuring direction of the domestic petrochemical industry. Major domestic petrochemical companies are accelerating production facility reductions and business restructuring under government guidance due to oversupply from China and sluggish global demand. The combined operating losses of the petrochemical divisions of Lotte Chemical, LG Chem, and Hanwha Solutions in the third quarter of this year amount to 436.9 billion won (KRW).


Despite this, S-Oil's decision to proceed with the Shahin Project as planned is interpreted as a judgment that it can secure long-term profitability based on differentiated cost competitiveness from existing facilities. Rather than waiting for market recovery, the strategy is to establish a high-efficiency production system to enhance competitiveness.


If global oversupply persists, there is a possibility that even with low-cost facilities, achieving profitability could be challenging. Ultimately, the success of the Shahin Project will depend on whether the cost competitiveness of the integrated refining and petrochemical processes can be translated into actual profits. Attention is focused on whether Aramco, poised to reap the benefits of large-scale investments amid instability in the Middle East and a global petrochemical downturn, can establish a new growth foundation through the Shahin Project.


Lee Deok-hwan, an emeritus professor of chemistry at Sogang University, stated, "It is an uncomfortable situation for large-scale new facilities to be operational while the petrochemical industry is undergoing restructuring. The government should actively ensure that the Shahin Project shares some of the social costs arising from compensating the pain of restructuring companies."





* This article has been translated by AI.