First Application of Government-Approved Price Contracts for Nuclear Power Next Year

Starting next year, a government-approved price contract (VC) will be introduced for electricity generated from nuclear power, allowing it to be traded at a predetermined standard price. This measure aims to reduce the financial uncertainties faced by Korea Electric Power Corporation (KEPCO) and Korea Hydro & Nuclear Power (KHNP) due to fluctuations in electricity market prices and to manage nuclear power generation revenues more rationally.


The Ministry of Climate, Energy and Environment will hold a ceremony on November 19 at KEPCO's Gyeongin Construction Headquarters in Jung-gu, Seoul, to commemorate the signing of the nuclear power government-approved price contract. This contract was initiated after KEPCO and KHNP signed the agreement on October 30, followed by the completion of the Electricity Commission's review on November 13. It will be implemented for five years starting January 1, following approval from the ministry.


The government-approved price contract is a system where power producers and electricity purchasers agree on the contracted power amount and standard price in advance, with the difference between the actual market price and the standard price settled afterward. If the market price is higher than the standard price, the power producer pays the difference to the electricity purchaser, and if the market price is lower, the purchaser compensates the power producer for the difference. Actual electricity will continue to be traded in the market according to the dispatch instructions of the electricity exchange.


The government-approved price contract was introduced with the amendment of the Electricity Business Act in 2014 and was applied to by-product gas generators of POSCO Energy and Hyundai Green Power from 2015 to 2020. However, this is the first time it will be applied to large-scale base power sources like nuclear power.


Under the existing settlement adjustment coefficient method, the rate of return on nuclear power investments and profit levels for power generation companies, including KHNP, could vary each year. The price contract is seen as a way to enhance the predictability of revenue during the contract period by reflecting the rate of return on investments in advance.


The ministry explained that this contract establishes a systematic basis for reasonably managing excess profits from nuclear power and ensuring that reduced electricity purchase costs can benefit consumers. In particular, it is expected that KHNP will strengthen investments in nuclear safety management based on revenue stability, while KEPCO will be able to reduce the volatility of electricity purchase costs.


Se-jin Ahn, head of the Energy Transition Policy Office at the ministry, stated, "To achieve the goal of 100GW of renewable energy, it is important to advance the electricity market," adding, "We will reform the market structure to harmonize contracts and the market, moving away from a spot market-centric approach."