Government Eases Regulations for AI Data Centers and Announces Legislative Proposal

The government will exempt artificial intelligence data centers (AIDC) with a contracted power of 50 megawatts (MW) or less located in non-capital areas from power system impact assessments. It will also establish a streamlined permitting process and relax installation standards for facilities such as parking lots.


On November 20, the Ministry of Science and ICT announced that it will propose a legislative draft for the enforcement decree and rules of the 'AIDC Special Act' by the end of next month.


The draft specifies the criteria for AIDCs eligible for support and special provisions under the special act. Facilities equipped with AI accelerators such as graphics processing units (GPU) and neural processing units (NPU), along with the necessary power and cooling equipment, will be included if they are designed to supply power to AI equipment at a certain scale.


Specifically, facilities must have an AI equipment power of 250 kilowatts (kW) or more, with at least 50% of the total information technology (IT) equipment power, or an AI equipment power of 5 MW or more. The ratio of total facility power to IT equipment power must be 1.5 or less. Co-location facilities that provide space and power, communication, and cooling equipment for AI racks owned and managed by other operators will also be included in the support criteria.


AIDCs that are newly constructed, expanded, or converted from existing facilities in non-capital areas will be exempt from power system impact assessments if they have a contracted power of 50 MW or less. A 'fast track' will be implemented for large-scale mega projects and AIDCs subject to streamlined permitting, prioritizing the assessment process. Facilities within AIDC special zones will also be exempt from non-technical evaluations.


The streamlined permitting process will involve the Ministry of Science and ICT requesting document reviews from relevant agencies within seven days of application. These agencies must respond within ten days regarding any necessary supplements. If they do not respond within the deadline, the process will proceed based on the submitted documents.


Measures will also be taken to prevent speculative businesses from merely taking advantage of special provisions. To this end, businesses must set a construction start date within one year from the date of construction notification. Operating notifications must be made 30 days prior to commencement, and changes must be reported within 30 days of occurrence.


Standards for installing parking lots will be relaxed by 20% compared to existing regulations, with the possibility of an additional 50% relaxation through municipal ordinances. In calculating the total floor area for the installation of artworks in buildings, the area of computer rooms and cooling equipment rooms will be excluded. In non-capital areas, the entire area will be excluded, while in capital areas, only half will be excluded.