The investment clock for domestic hyperscale artificial intelligence data centers (AIDC) has come to a halt. Due to delays in permits such as power transmission, construction periods are extending, causing financial costs to balloon, leading companies to postpone funding and construction.
According to the IT industry on November 22, among companies planning hyperscale AIDCs, only SK Group has issued corporate bonds for AIDC purposes up to the third quarter of this year. Most funding through financial investors (FIs) remains in the negotiation stage.
KT plans to secure over 80% of the approximately 87 trillion won (KRW) needed for a 1-gigawatt (GW) AIDC from external sources and is in discussions with multiple investors. However, it appears that the company has not yet decided on its own investment amount. LG Uplus has secured 2 trillion won (KRW) of the approximately 18 trillion won (KRW) it needs, while Kakao has obtained around 600 billion won (KRW) of the 7 trillion won (KRW) required for its 80 MW facility, but has not confirmed its own investment through corporate bond issuance.
In July, Naver entered into a $1 billion equity investment agreement with NVIDIA, and in its August earnings announcement, it selected Brookfield as the exclusive preferred negotiator. Brookfield plans to establish a special purpose company to secure GPUs and data centers worth up to $9 billion, with a formal contract signed on October 27, after the third quarter ended. Naver has also not issued corporate bonds.
The industry explains that companies are being cautious about funding due to uncertainties surrounding permits. If construction begins this year but halts due to delays in permits such as power transmission, interest costs on already invested construction funds accumulate daily. The routes for high-voltage lines, which are pursued separately from data center buildings, are often only revealed after construction begins, making it difficult for operators to anticipate permit conflicts.
The industry estimates that the cost of construction delays is approximately 300 million won (KRW) per day, assuming construction costs of 1 trillion won (KRW), and about 600 million won (KRW) per day for 2 trillion won (KRW). Over a month, this amounts to about 9 billion won (KRW), and over six months, approximately 54 billion won (KRW) increases, with a one-year delay adding 1.1 billion won (KRW), which is 11% of the construction costs.
According to the financial sector, the interest rate for senior project financing (PF) loans for hyperscale data centers is in the low 5% to low 6% range, while junior and mezzanine financing is around 7% to 8%. The Gunsan 60 MW AI data center, in which Korea Investment & Securities participated as the financial advisor for FI interest, is entirely leased by KT Cloud, which secured 6.576 trillion won (KRW) in main PF at a low 5% interest rate in October.
Companies are reportedly planning to wait and see the market conditions next year rather than bringing in FIs to start construction now. They believe that securing funds before resolving permit issues could lead to increased interest costs due to prolonged timelines and complex approval processes.
An IT industry official stated, "Rather than starting construction immediately after borrowing, there is a sentiment to begin in regions where permits are easier, and to start construction for major AIDCs in the metropolitan area after the AIDC special law takes effect in March next year. It is rational to start construction once permits are clarified, as raising corporate bonds or FIs beforehand could increase interest burdens."