The opposition movement against artificial intelligence data centers (AIDC) is intensifying in South Korea, led by civic groups. AIDC power lines require permits from each district they pass through, and many construction sites are facing the risk of halting work due to local opposition.
Local governments are hesitant to upset civic groups ahead of the AIDC special law (Special Act on the Promotion of the AI Data Center Industry), which will take effect in March next year. Concerns are growing that the construction timeline for major AIDC projects in the country could be delayed by more than six months.
According to the IT industry on November 22, the 99-megawatt (MW) AIDC project in the Naedong area of Bucheon is struggling due to the lack of approval for power line installation in Bupyeong.
This AIDC will receive 80 MW of power from the Bupyeong Galsan Substation. A 154-kilovolt (kV) high-voltage line (which exceeds 7,000 volts) needs to be buried underground from the substation to the AIDC. While Bucheon City, the Han River Basin Environmental Office, and Ojeong-gu in Bucheon have granted their approvals, Bupyeong has yet to issue its permit.
Bupyeong rejected the application in February 2024, attaching a condition to review changing the power supply source to the substation within Bucheon. A new application was submitted this year, but the district did not present it for review in the fourth quarter, citing that the condition had not been met.
Industry insiders point to civic group opposition as the reason for the halted approvals. A local government official stated, “Ahead of the AIDC special law, Bupyeong is avoiding permits for burdensome projects. Civic groups are also working in an organized manner with local media, which is causing disruptions to the construction itself.”
The AIDC project is expected to invest approximately 1.4 trillion won (KRW) in construction, and when including equipment such as graphics cards, the total project scale is about 5 trillion won (KRW). While the goal is to commence operations in April next year, construction delays are inevitable without Bupyeong's approval. A site official explained that if construction is delayed, the additional costs incurred per day would reach 390 million won (KRW).
Bucheon’s AIDC is not the only one facing such difficulties. In Incheon’s Michuhol District, a high-voltage line supplying electricity to a maximum 80 MW data center stretches about 4.7 km through Seonin High School and Inhwa Middle School. About 6,400 residents participated in a petition against the project, and in May, three resident representatives shaved their heads to demand the project be scrapped.
In Incheon’s Seohae District, a 5.5 km 154 kV power line connecting the Gajwa-dong data center and the Wonchang Substation passes near elementary schools and apartment complexes, leading to backlash from parents. An 'electromagnetic wave traffic light' that publicly displays electromagnetic wave levels 24/7 has been introduced.
There have also been instances where construction was temporarily halted. In Anyang, a civic group filed a request for an audit with the Board of Audit and Inspection regarding a 7 km underground 154 kV line supplying power to LG Uplus's Pyeongchon 2 Center in 2023. The construction was paused but resumed after an agreement was reached between Anyang City and citizens to install shielding panels along the line.
In Gimpo’s Gurae-dong, residents opposed the installation of a high-voltage line just 100 meters from an elementary school, and the Gyeonggi Province Administrative Appeals Commission deemed the rejection of Gimpo City’s construction notification in October 2024 as unjust, leading to ongoing conflicts.
The background of these conflicts lies in regulatory gaps. Starting in March next year, when the AIDC special law takes effect, government agencies will be able to handle permits collectively. However, until then, all local governments along the power line route, as well as related agencies, must grant approval, meaning that if just one entity opposes, the power line cannot be installed.
An official from an AIDC investment company noted, “If construction starts this year, the difficulties related to power line procedures will be significant, so most companies are inclined to begin in April next year. Even with the government's collective approval, it is highly likely that construction will not start until the end of the year, which ultimately means that South Korea's AIDC industry will be delayed by at least a year due to local government approval issues.”