The cables will be delivered through its North American unit, LS Cable & System USA, for Propel NY Energy, an about 145-kilometer grid linking Long Island with Queens, the Bronx and Westchester County.
The project, jointly driven by the New York Power Authority and transmission developer New York Transco, moved into full swing after state authorities recently approved its construction plan, following a contract signed in February.
LS Cable will deliver the cables and carry out electrical work and commissioning tests. It is the only Korean cable maker with a track record of supplying extra-high-voltage submarine cables overseas.
The order comes as power-hungry data centers strain grids on both sides of the Pacific, keeping cable orders brisk even as questions mount over the AI investment boom.
Seoul last week moved to fast-track grid reviews for AI data centers, targeting 8.4 gigawatts of capacity by 2029.
"In integrated subsea and onshore transmission projects, the ability to both supply and install extra-high-voltage cables is the core competitive edge," an LS Cable official said, adding the company would actively pursue next-generation grid projects at home.
Copyright ⓒ Aju Press All rights reserved.